Three Things That Decide a Northeast Ohio Job
The number that changes everything is one acre. Unlike states that set a
square-footage trigger, Ohio hangs most of its paperwork on the acre. Ohio Revised Code 307.79
lets county commissioners require plans governing erosion control, sediment control and water
management before clearing, grading, excavating, filling or otherwise wholly or partially
disturbing one or more contiguous acres of land for nonfarm uses, and it adds that areas of
less than one contiguous acre are not thereby exempt from the rest of the rule. Inside the city,
the Division of Construction Permitting lists a stormwater pollution prevention plan as required
for sediment and erosion control and post-construction stormwater management where the disturbed
area is greater than one acre. Cuyahoga Soil and Water Conservation District reviews those plans
for sites disturbing one or more acres, and Ohio EPA coverage reaches under an acre when the work
sits inside a larger common plan of development or sale. Ohio EPA also states plainly that local
jurisdictions may have more stringent requirements. Requirements vary by parcel, scope and
jurisdiction, and the governing authority makes the determination. The sequence is laid out in
our Cleveland and
Cuyahoga County permit guide.
A stream on the parcel can move the work line by hundreds of feet. This is the
one that catches owners east of the city. Chagrin River Watershed Partners publishes a model
riparian setback ordinance whose setbacks vary from 25 to 300 feet from either side of the
stream, and inside that strip building and other soil disturbing activities are prohibited
unless the applicant obtains a variance. Communities adopt it one at a time, so whether a
setback governs your ditch, creek or river is a question about your own community rather than
about the watershed, and it is worth asking before a machine is booked rather than after a stop
work notice. Where a setback does apply, the scope usually changes shape rather than
disappearing: selective cutting, work kept back from the bank, and a wider strip left standing.
The ground is wet from October through June, and that sets the schedule. The
USDA description of the Mahoning series is unusually blunt about it: a perched or apparent
seasonal high water table can be present from 15 to 30 cm, which is 6 to 12 inches, below the
surface from October through June in most years, on slopes of 0 to 15 percent, with saturated
hydraulic conductivity moderately low in the subsoil and moderately low or low in the material
underneath. Water sitting inches down on a dense floor means a tracked machine marks a surface
in spring that it would have crossed cleanly in late summer, and it means loaded trucks are the
worst possible way to get material off a parcel in April. Two windows genuinely work here: dry
late summer, and ground frozen hard enough to carry weight. That is the argument for chipping
material in place, and it is covered properly in our guide to
clearing wet
ground in Northeast Ohio.