What to Know Before Clearing Land Around Hopewell
River and creek frontage is protected. Hopewell maps Chesapeake Bay preservation
areas to protect the James, the Appomattox and the water that drains to them, with a 100-foot
buffer on both sides of any stream that flows year-round. Removing vegetation inside that buffer
needs review and approval by the Director of Development, and when a quarter of a lot falls in the
protected area the whole lot follows the rules. Prince George County applies its own standards in
Bay protection areas too. A waterfront clearing line is drawn after the map is checked, not before.
Old fields turn to sweetgum and mimosa. Sweetgum is often the first tree into an
idle Coastal Plain field, and mimosa takes to old fields, roadsides and forest edges here. Both
sprout from their roots once cut, so a single pass leaves a field green again by the next summer.
We price the first pass in its band and list each sprout visit separately.
Offices and permits. In the City of Hopewell, disturbing 2,500 square feet or more
of land needs a City Land Disturbing Permit, and one acre or more also needs the city's VSMP
stormwater permit. In Prince George County, the Environmental Division of Community Development
requires an approved erosion and sediment control plan once land-disturbing work reaches 2,500
square feet. Requirements vary by parcel, scope and jurisdiction, and the governing authority makes the
determination.